A China sourcing schedule needs more than a factory’s holiday dates. Component suppliers, inspection teams, carriers and payment-processing contacts may have different cut-offs. For an order spanning National Day or Chinese New Year, work backwards from when the goods must be usable in Japan.
Define the date that matters to your business
Distinguish arrival at your warehouse from delivery to a shop or exhibition venue. Allow for any assembly, kitting and onward distribution after receipt. Record the required quantity and the non-negotiable date for each item. This makes it easier to identify which products genuinely need priority.
Confirm four cut-offs with each supplier
- The order and payment deadline for securing materials.
- The specification and sample-approval deadline for production.
- The last inspection date that still leaves room for corrections and rechecking.
- The final handover date accepted by the chosen carrier.
If a supplier says an order will be “finished before the holiday”, ask what finished means. Production completed, goods inspected and cartons ready for collection are different milestones. Mark whether each date uses China or Japan time, and keep unconfirmed dates visibly unconfirmed.
Calculate shortages by item
Start with usable stock, subtract quantities already committed to existing orders, and add receipts confirmed to be available before the required date. Compare that balance with planned sales or project consumption. Keep uncertain inbound quantities separate so they do not create a false impression of stock coverage.
For a gift set, review the bottle, pump, label and printed box together. Having every bottle in stock does not make the set ready if the custom box is still missing. A component-level view can reveal the real constraint before you place another order for finished goods.
Compare one delivery with a split shipment
Prepare two options: wait for the complete order, or send the quantity needed first and release the balance later. Compare freight, repeated packing, inspection arrangements and receiving work in Japan. If air freight is an option, confirm product restrictions, available capacity and collection deadlines before treating it as a recovery plan.
A tight schedule should not silently turn into permission to substitute an unapproved material or omit an agreed inspection. Put the proposed change, its cost and its quality implications in front of the person who can approve it. The decision should be explicit before work proceeds.
Plan the first update after reopening
A supplier’s reopening date is not necessarily the day your order enters production. Ask for material availability, the production slot, remaining work and a revised dispatch estimate. Add the next question, its owner and the expected response date to the schedule. This helps both sides focus on the same unresolved task.
For an initial discussion, prepare the item list, quantities, required date in Japan, specification status and whether split delivery is acceptable. Holiday arrangements and transport schedules vary by year, supplier and service. Confirm the dates that apply to your actual order rather than carrying forward last year’s calendar.
